Project: 92a Mill Road
Client: Taank Optometrists
Consultant: Layrd Design
Contract Period: 22 weeks
Description: The project at 92A Mill Road, Cambridge involved the demolition, structural redevelopment, and refurbishment of an existing building. The scope of work included site preparation, demolition of existing structures, excavation, and foundation construction, followed by the erection of new sub-structures and superstructures. The project also encompassed masonry, roofing, internal and external partitions, mechanical and electrical installations, and high-quality finishes.
Key aspects of the project included:
-Demolition & Site Preparation – Existing internal fit-out was removed, asbestos was safely handled, and foundation excavation was carried out.
-Structural Works – New foundations were constructed, reinforced concrete structures were installed, steel framing was erected, and roof modifications were completed.
-Mechanical & Electrical Installations – A new drainage system, HVAC, lighting, and fire safety systems were installed.
-Internal & External Finishes – New windows, doors, flooring, wall finishes, and decorative elements were added.
-Compliance & Safety – All work adhered to Building Control, Party Wall regulations, and fire safety requirements.
The project successfully modernised and enhanced the property while ensuring compliance with all relevant safety and construction standards.